9 Dec – 13 Jan2025 to 2026, with the office closed over Christmas
Openevery working day; we worked evenings and weekends
Hanex + FinsaToffee Crunch solid surface, Lisa Oak panels
Both sidespublic counters and the staff side behind them
02 · How we got the job
Recommended by our supplier
The contractor leading the project was pointed to us by the supplier we both buy from, on the strength of our solid surface work. We agreed between us who would do which part, tendered together for the public contract and won it. Our part was the counters.
05 · Timeline
Workshop by day, site until midnight
Workshop preparation started the day the material arrived. From 9 December 2025 we worked in our workshop from the morning until 5 pm, then went to the Intreo Centre and worked there until midnight. At weekends we spent the whole day on site. That is how the office kept running for staff and the public. It closed between Christmas and New Year, so we stopped too. Everything was finished on 13 January 2026.