A garden building rotting from the inside, brought back to life
A self-contained studio in a garden in Co. Kildare: mould on the walls and rot under every floorboard. The cause was hidden under the floor. We stripped the building back to the blockwork and rebuilt it from the ground up.
Down to the blockevery finish stripped out
New floordrainage, membrane, joists, insulation
May–July 2024start to finish
Facebookhow the owners found us
01 · What we found
Mould on the walls, rot under the floor
A self-contained studio in a garden in Co. Kildare. The owners had seen some of our earlier work on Facebook and called us. Black mould on the walls, damp around the radiator, a shower room rotting from below and a floor that gave under your feet.
The studio as we found it.
Mould on the walls.The old shower room.Rot under the shower.
Damp behind the radiator.The old skylight.
02 · The cause
One nail
When the building went up 26 years ago, a nail was driven through a water pipe under the floor. For 26 years it leaked, slowly and out of sight, until the whole room had rotted from underneath. We found it the day we lifted the floor.
The cause: a nail through the water pipe, leaking for 26 years.
Rotten floorboards.Floor lifted.
Rot at the base of the wall.Rotten joists.
03 · Strip-out
Back to the block
Patching would only have hidden the problem. We stripped the building back to the blockwork: floor, walls, ceiling, shower room, the lot.
Stripped to the block.Bare block and roof, skylight still in.
04 · The floor
A new floor from the ground up
New drainage and a new water supply under the floor, a damp-proof membrane, new timber joists, insulation between them and an OSB deck on top.
New drainage.New joists on the membrane.
Insulation between the joists.OSB deck on top.
05 · Walls and ceiling
Insulated, boarded, and the skylight closed off
Insulated stud walls inside the blockwork, an insulated ceiling with a vapour barrier, and the old skylight sealed and closed off. Then everything was boarded.
The new ceiling, skylight closed off.
Wall insulation.Walls and ceiling boarded.
06 · Shower room
Waterproofed before a single tile
New shower drain, the whole shower area waterproofed, then the tray, shower, vanity and WC.
New shower drain.
Shower area waterproofed.The shower room, finished.
07 · Finished
A dry, warm studio
A kitchenette we made and fitted ourselves, new radiators with part of the heating pipework adapted and replaced, new doors and a laminate floor.
The studio, finished.
Kitchenette, made and fitted by us.Into the shower room.
The shower.WC and vanity.The new floor.
The finish level was the owners’ choice. What this job shows is what goes on underneath, and that part we do the same way on every job.